The Act provides a national policy and program to preserve and protect selected rivers, or segments of rivers, in their free-flowing condition in the National Wild & Scenic Rivers System.  Section 1(b) of the Act states:

It is hereby declared to be the policy of the United States that certain selected rivers of the Nation which, with their immediate environments possess outstandingly remarkable scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar values, shall be preserved in free-flowing condition, and that they and...

Yes.  For purposes of eligibility evaluation, the volume of flow is sufficient if it is enough to sustain or complement the outstandingly remarkable values identified within the segment.  Rivers with intermittent or non-perennial flows exist within the National Wild & Scenic Rivers System and may be representative of rivers within particular physiographic regions.

Section 4(a) of the Wild & Scenic Rivers Act and the Interagency Guidelines describe and discuss content requirements, specific topics to be addressed, and the way in which information should be presented in such a study report. The National Environmental Policy Act (NEPA) process can, and is, readily merged with the requirements of the wild and scenic river study report. A wild and scenic river study report resulting from a decision in a land management plan usually summarizes and incorporates relevant information from the plan and associated NEPA document. For example, the location...

Camping is often important to the enjoyment of wild and scenic rivers. As appropriate, and when private interests do not provide sufficient facilities, the federal managing agency attempts to provide them on federal lands. As a condition of use, consistent with river classification and the management objectives for the river area, the managing agency may specify that camping will be permitted only in designated locations. Enforcement of camping restrictions and limitations can be through indirect means (brochures, maps, signs, etc.) and/or direct means (permits, enforcement personnel, etc...

Yes. The Wild & Scenic Rivers Act directs other federal agencies to protect river values. It explicitly recognizes the regulatory roles of the Federal Energy Regulatory Commission and the Environmental Protection Agency in protecting wild and scenic rivers, and directs other federal departments and agencies that permit or assist in the construction of water resources projects to do likewise. The role of such federal agencies in water resources project construction may be through regulation, direct funding, or indirectly funding by providing federal assistance to others.

All...

Wild and scenic river designations generally cause property values to remain stable or increase. For example, see Economic Benefits of Conserved Rivers: An Annotated Bibliography (Porter, B., Collier, S., Becerra, N., and Schultz, J. 2001. National Park Service – Rivers and Trails Conservation and Assistance Program, Washington, DC. 27pp.).

The Wild & Scenic Rivers Act requires that detailed boundaries portrayed on maps be established and submitted to Congress within one year of designation. Agencies may finalize boundaries through their respective land management planning process.

Pending the establishment of detailed river boundaries, the Wild & Scenic Rivers Act specifies that the interim boundary is one-quarter mile on each side of the river as measured from the ordinary high water mark.

Section 3(b) of the Wild & Scenic Rivers Act states:

The agency charged with the...

Regardless of the study agency’s eligibility and suitability findings, a Section 5(a) study river is protected by the conditions and restrictions specified in Sections 7(b), 8(b), 9(b), and 12(a) of the Wild & Scenic Rivers Act during the period of the study, plus up to three years after the required report is submitted to Congress. In other words, these protections are independent of the recommendation of the study, allowing for Congressional consideration.

The requirement for a comprehensive river management plan (CRMP), does not apply to state-administered, federally designated rivers. Federal land managers are responsible for protecting river values in all agency planning and management actions for any portion of a 2(a)(ii) river that flows on federal lands. In some cases, the petitioning state has a requirement for a plan. The existence of a state or local plan to protect river values is one of the factors considered by the National Park Service in its review of the 2(a)(ii) nomination for the Secretary.

The need to clarify the terminus should be identified as a management concern/public issue during the planning process and considered in establishment of the initial boundary. The proposed clarification associated with establishment of initial boundaries must be undertaken with full public input and disclosure and is often completed during development of the comprehensive river management plan (CRMP).

In rare instances where the agency did not define the terminus to fit on-the-ground practicalities (e.g., a terminus described in legislation as “from the dam” included a dam and dam-...

The CRMP for rivers designated on or after January 1, 1986, is to be completed within three full-fiscal years after the date of designation or as otherwise specified, with a notice of completion and availability published in the Federal Register. For rivers designated before this date, Section 3(d)(2) requires review of the CRMP to determine if it conforms to Section 3(d)(1). This provision allowed ten years to update pre-1986 plans through the planning processes of river-administering agencies. Note: This 10-year period expired January 1, 1996.

Corridors may not exceed an average of 320 acres per river mile over the designated portion of the river (except on certain other rivers as specified by Congress and in Alaska, which is 640 acres for rivers located outside national parks). Agencies delineate boundaries based on natural or manmade features (canyon rims, roads and ridge tops, etc.) and legally identifiable property lines.

Section 13(g) of the Wild & Scenic Rivers Act allows the granting of easements and rights-of-way within the boundaries of designated components in accordance with applicable laws, provided that the conditions attached to the grant are consistent with the purposes of the Wild & Scenic Rivers Act.

Any portion of a right-of-way project that includes federally assisted construction that may affect the river’s free-flowing condition—and is not automatically prohibited by the Wild & Scenic Rivers Act—is subject to an evaluation by the river-administering agency under Section...

No. Lands owned by a state may be acquired only by donation or exchange per Section 6(a)(1) of the Wild & Scenic Rivers Act.

Yes, the federal government may seek to control use on adjacent lands under very limited circumstances. The Constitution gives the federal government certain limited powers to control uses on state-owned lands that affect adjacent federal property. These powers may be exercised through the Property Clause, which provides that, “Congress shall have the power to make all needful rules and regulations respecting the territory or the property belonging to the United States.”

The federal government may also regulate use and/or activities occurring on the surface waters...

The need to clarify a segment division should be identified as a management concern/public issue during the planning process and considered in establishment of the initial boundary. The proposed clarification associated with establishment of initial boundaries must be undertaken with full public input and disclosure and is often completed during development of the comprehensive river management plan (CRMP).

In rare instances where the agency did not define the segment division to fit on-the-ground practicalities (e.g., a terminus described in legislation as “from the bridge”...

Upon congressional authorization for a study (Section 5(a)) or by federal agency initiative (Section 5(d)(1)).

Congress may classify the river upon the date of designation or authorize classification by the managing agency.  In the latter case, managing agencies have one year to finalize the boundary, identify the appropriate classification, and publish a notice in the Federal Register.  The agency has three years to complete a management plan.  For Section 2(a)(ii) rivers, classification would be established when the Secretary of the Interior designates the river.

Suitability is an assessment of factors to provide the basis for determining whether to recommend a river for addition to the National Wild & Scenic Rivers System. Suitability is designed to answer these questions:

  1. Should the river’s free-flowing character, water quality, and outstandingly remarkable values (ORVs) be protected, or are one or more other uses important enough to warrant doing otherwise?

  2. Will the river’s free-flowing character, water quality, and ORVs be protected through designation? Is it the best method for protecting the river corridor...

Once such a river segment has been found to be ineligible, the agency will manage the river and its corridor based on the underlying management direction in its programmatic plan and need no longer protect it as a potential wild and scenic river.

No restrictions to private lands may be applied under the Wild & Scenic Rivers Act. Comprehensive river management plans may establish goals for new construction consistent with classification. There is a wide range of uses compatible with these classifications so long as the overall values and character of the river corridor is maintained. Any effect on private lands would be through state or local zoning. Federal acquisition of lands or development rights would require landowner compensation.

River access is evaluated in the land use planning process.  Specific access needs for public enjoyment, as well as any limitations, are determined in the river management plan.  In keeping with the requirements of the Wild & Scenic Rivers Act, “wild” rivers are generally inaccessible, except by trail (no roads); “scenic” rivers are accessible by road, which generally don’t parallel the river; and “recreational” rivers may have parallel or crossing road and railroad access.

Yes. In some river study authorizations Congress has required the study agency to work with state and local governments and the public to develop a CRMP in concert with the study process to assist in determination of the river’s suitability. Such pre-designation CRMPs have, in some cases, been adopted in the legislation adding the river to the National Wild & Scenic Rivers System. In cases where Congress has not authorized a pre-designation CRMP, agencies have taken the initiative to develop elements of the CRMP in the study report (pre-designation).

As provided in Sections 4(a) and 5(c) of the Wild & Scenic Rivers Act, the following factors should be considered and, as appropriate, documented as a basis for the suitability determination for each river.

  1. Characteristics which do or do not make the area a worthy addition to the National Wild & Scenic Rivers System. These characteristics are described in the Wild & Scenic Rivers Act (see factors 2 through 7) and may include additional suitability factors (8 through 13).

  2. The current status of land ownership and use in the area.

  3. The...

Yes. Legal descriptions along with a map are submitted to Congress in accordance with Sections 3(b) and (c) of the Wild & Scenic Rivers Act and are retained by the administering agency. Requests for maps should be made to the agency field offices which administer the specific study or designated river(s).

No. Federal agencies do not have the authority to reimburse landowners for damage to their lands as a result of public use. However, wild and scenic river designation is unlikely to increase or invite vandalism. Granting access remains the owner’s responsibility and vandalism is handled by local law enforcement authorities. Federal river-administering agencies do, however, work closely with landowners to minimize problems through brochures and maps, signs, etc., and many landowners feel they are better off with the agency taking some responsibility.

Section 4(f) refers to the original section within the United States Department of Transportation (DOT) Act of 1966 (49 U.S.C. Section 303(c); 23 U.S.C. Section 138). The DOT Act was enacted to ensure that transportation plans and programs include measures to maintain or enhance the natural beauty of publicly owned public parks, recreation areas, wildlife/waterfowl refuges, and historic sites of local, state, or national significance transversed by highways.

Yes. Water may be secured through a variety of protection strategies, in the interim. Ultimately, the United States should secure a federal reserved water right in state court or the appropriate forum. Interim measures may include, but are not limited to: state instream flow programs, reservoir operation schedules, endangered species flow recommendations, conservation techniques, cooperative agreements, and water right purchases from willing sellers.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water...

For rivers designated under Section 3(a) of the Wild & Scenic Rivers Act, a state’s responsibilities include:

  • Regulating and enforcing fishing and hunting regulations.

  • Adjudicating water rights and appropriation.

  • Developing and administering water quality standards.

  • Administering state land use regulations on non-federal lands.
  • Managing state lands and facilities along the river (e.g., state highways, parks, forests).

No.  The Interagency Wild & Scenic River Guidelines state, “There are no specific requirements concerning the length or the flow of an eligible river segment.  A river segment is of sufficient length if, when managed as a wild, scenic or recreational river area, the outstandingly remarkable values are protected.  Flows are sufficient if they sustain or complement the outstandingly remarkable values for which the river was designated.

Land acquisition is one tool for protecting and enhancing river values. It may also be an important means of providing public access to a wild and scenic river. Notwithstanding Section 6 of the Wild & Scenic Rivers Act, however, Congress has pre-empted some or all of the Wild & Scenic Rivers Act’s federal land acquisition authorities in the enabling acts for certain wild and scenic rivers where the river study demonstrated that protective zoning or other conservation practices provided adequate safeguards for river values.

There are more appropriate and cost-effective ways to ensure resource conservation along wild and scenic rivers than using the Wild & Scenic Rivers Act’s condemnation authority. (Refer to Protecting Resource Values on Non-federal Lands (1996).)

Agencies may acquire properties using appropriated funds under the Land and Water Conservation Fund Act or other authorities. Owners are contacted in order to see if an exchange or voluntary purchase can be negotiated.

Section 13(c) of the Wild & Scenic Rivers Act expressly reserves the quantity of water necessary to protect river values, including water quality and flow-dependent outstandingly remarkable values. This reservation of water is called a federal reserved water right and is generally adjudicated in a state court (e.g., basin-wide adjudication). River designation does not supersede existing, valid water rights.

Refer also to CRS Report for Congress, The Wild and Scenic Rivers Act and Federal Water Rights, by Cynthia Brougher (January 9, 2009).

 

...

The need to amend a segment division should be identified as a management concern/public issue during the planning process and considered in establishment of the initial boundary. The proposed amendment associated with establishment of initial boundaries must be undertaken with full public input and disclosure and is often completed during development of the comprehensive river management plan (CRMP) as a basis to make a recommendation to Congress to amend the Wild & Scenic Rivers Act.

The river-administering agency can only recommend such a change to Congress. A subsequent...

Yes. There are four other principal agencies with authority on rivers, including wild and scenic rivers, in the United States. The EPA has authority to protect water quality; the Army Corps of Engineers (ACOE) has jurisdiction for water resources projects; the U.S. Coast Guard (USCG) has jurisdiction on inland navigable waters, vessel inspecting and licensing, safety and boating enforcement, aids to navigation, and permitting of bridges; and the Federal Energy Regulatory Commission (FERC) has authority to license the construction of hydroelectric projects.

On September 7, 1982, the Departments of Agriculture and the Interior outlined in the Federal Register (47 FR 39454) eligibility and classification criteria, the evaluation process and content, and reporting requirements for potential wild and scenic rivers and management guidelines for designated wild and scenic rivers. These guidelines were formulated to provide a uniform evaluation and consistent management approach in the identification, evaluation, reporting, and management of wild and scenic river segments. These replaced earlier guidelines developed in 1970.

Yes. Fishing and hunting are regulated under state laws. Where hunting and fishing were allowed prior to designation, they may continue. The river-administering Secretary may, however, designate no hunting zones or periods in which no hunting is allowed for public safety or other reasons. The Secretary must issue such regulation in consultation with the wildlife agency of the state(s).

Once rivers have been evaluated and determined eligible for further study, agencies conduct an evaluation to determine if the rivers are “suitable” or “not suitable” for wild and scenic river designation within their resource or land management planning processes (Section 5(d)(1)), or usually as a separate study for congressionally authorized studies (Section 5(a)). In each process, the benefits of protecting river values are weighed against other resource values, issues and alternatives.

Either process is typically accompanied by an environmental document, normally an...

The study report for a congressionally authorized Section 5(a) study river is required to be forwarded by the study agency within the period specified in Section 5(b). This study report must be forwarded to Congress no matter what the outcome of the study.

Unlike the firm deadlines established for Section 5(a) study reports, the Act is silent in regard to Section 5(d)(1) rivers. Thus the river-administering agencies have considerable latitude in how and when to transmit the study report for rivers they have found suitable and are recommending to Congress for designation. The...

No. The protection afforded by Section 7(b) of the Wild & Scenic Rivers Act does not apply to Section 5(d)(1) study rivers. However, the managing agency should, within its authorities, protect the values which make the river eligible or suitable (free-flowing condition, water quality and outstandingly remarkable values).

Review of hydroelectric and federally water resources projects under Section 7 of the Wild & Scenic Rivers Act is complex. Please refer to Wild & Scenic Rivers Act: Section 7 (2004), a technical report of the Interagency Wild and Scenic Rivers...

As of June 2022, some 226 river segments comprising 13,417 miles have been afforded protection in the National System.  These nationally recognized rivers comprise some of the nation’s greatest diversity of recreational, natural, and cultural resources, offering great scientific value and scenic beauty.  By comparison, more than 75,000 large dams across the country have modified at least 600,000 miles, or about 17% of America’s rivers (possibly more than 20% – figures are best estimates).

Timber management activities on federal lands outside the corridor are managed to protect and enhance the values that caused the river to be designated. Measures needed to protect and enhance the river’s values are developed through the river planning process and include management direction as necessary for lands adjacent to the corridor.

No. Non-indigenous species need not be removed unless they are degrading other important resource values. Practical considerations, such as the effort or expense of eradicating a non-indigenous species and its importance (e.g., game species), should also be considered. This issue is generally addressed in the management plan.

Many individuals and communities support designation to help focus management efforts on protecting and enhancing river values. The intent of the Wild & Scenic Rivers Act is to build partnerships among landowners, river users, tribal nations and all levels of governments in developing goals for river protection. Designation provides strong protection against construction of new dams and projects that alter the free-flowing condition, water quality, and outstandingly remarkable values for which the river was designated.

Yes. Section 6(b) of the Wild & Scenic Rivers Act specifically prohibits the use of condemnation for fee title purchase of private lands if 50 percent or more of the acreage within the boundaries on both sides of the designated river is in public ownership (i.e., owned by the federal, state, or local government). In addition, Section 6(a)(1) of the Wild & Scenic Rivers Act prohibits acquiring more than 100 acres per river mile within the corridor, which equates to a stip of land about 400-feet wide along both sides of the river. Fee title condemnation is allowed to clear title or...

Through the various federal agencies’ land management planning processes and initiatives by the public, a significant number of rivers have been identified for study as potential additions to the National Wild & Scenic Rivers System. For example, the Nationwide Rivers Inventory (NRI), maintained by the National Park Service, has identified over 3,400 river segments as potential candidates for study and/or inclusion into the National System.

Citizen stewards are increasingly important in protecting wild and scenic river values, often through river-specific or regional stewardship organizations. Individually, or through nonprofit entities, citizens help survey and monitor resource conditions, provide interpretive and education opportunities, contribute to restoration efforts, and support many other protection activities.

Agency land use or resource management plan records should include documentation of the eligibility criteria, inventory process, evaluation, and outcome. Agency field offices retain the administrative record and documents related to an assessment of the free-flowing condition and identification of outstandingly remarkable values.

Most current uses and activities on rivers and adjoining federal lands may continue. Of primary consideration in any river or land-use limitation is the protection and enhancement of the free-flowing condition, water quality, and outstandingly remarkable value(s) that resulted in the river’s designation. Those uses that clearly threaten these values will be addressed in the planning process, or through site-specific environmental analyses on a case-by-case basis where federal lands are involved.

No, there is no statutory requirement that a CRMP be revisited in a specified timeframe. However, the federal wild and scenic river-administrator should periodically review monitoring information to determine if there is a need for change in existing direction to ensure values are protected and enhanced. Agency unit-wide plans that are revised following a CRMP-specific plan amendment will follow individual agency practices for plan revision. In some cases, this may include updating the CRMP during the agency unit-plan revision cycle.