The Act provides a national policy and program to preserve and protect selected rivers, or segments of rivers, in their free-flowing condition in the National Wild & Scenic Rivers System.  Section 1(b) of the Act states:

It is hereby declared to be the policy of the United States that certain selected rivers of the Nation which, with their immediate environments possess outstandingly remarkable scenic, recreational, geologic, fish and wildlife, historic, cultural, or other similar values, shall be preserved in free-flowing condition, and that they and...

The Wild & Scenic Rivers Act expressly prohibits the Federal Energy Regulatory Commission (FERC) from licensing the construction of a hydroelectric project or project works (e.g., facilities such as the powerhouse, access roads, transmission lines) under Part 1 of the Federal Power Act “on or directly affecting” a designated wild and scenic river. However, on the few rivers with a FERC-licensed hydroelectric project/project works within the river’s boundaries at the time of designation, existing operations may continue.

Relicensing of existing FERC-licensed hydroelectric...

Citizen stewards are increasingly important in protecting wild and scenic river values, often through river-specific or regional stewardship organizations. Individually, or through nonprofit entities, citizens help survey and monitor resource conditions, provide interpretive and education opportunities, contribute to restoration efforts, and support many other protection activities.

Timber management activities on federal lands outside the corridor are managed to protect and enhance the values that caused the river to be designated. Measures needed to protect and enhance the river’s values are developed through the river planning process and include management direction as necessary for lands adjacent to the corridor.

On September 7, 1982, the Departments of Agriculture and the Interior outlined in the Federal Register (47 FR 39454) eligibility and classification criteria, the evaluation process and content, and reporting requirements for potential wild and scenic rivers and management guidelines for designated wild and scenic rivers. These guidelines were formulated to provide a uniform evaluation and consistent management approach in the identification, evaluation, reporting, and management of wild and scenic river segments. These replaced earlier guidelines developed in 1970.

Yes, if they are consistent with management objectives for the river and do not degrade water quality or the outstandingly remarkable values for which the river was designated.

A Section 5(d)(1) study river is protected to the extent of each study agency’s authority and not by the Wild & Scenic Rivers Act. Each agency’s policy is to protect eligible rivers and rivers determined suitable for designation for the life of the respective agency land use plan. A river determined not suitable for designation need no longer be protected as a potential addition to the National Wild & Scenic Rivers System once the study, with its related decision document, is completed.

There are a number of steps that federal agencies use in their evaluation process:

  • Assessment of free-flowing condition and resource values.
  • Finding of eligibility or ineligibility.
  • Inventoried or tentative classification based on the development of shoreline, watercourse, and access.
  • Establishment of tentative, preliminary, or proposed boundaries and/or river areas.
  • Establishment of protective management requirements for eligible rivers.

Generally, no. Restrictions on public boating access and the implementation of entry permit systems (rationing and/or allocation) are not usually related to designation. Limitations on boating usually relate to the amount of use and/or types of user. Those rivers with use levels or types of use beyond acceptable limits (i.e., resulting in impacts to the values) may necessitate restricted access regardless of designation.

Administering agencies do not have any authority to control public use of private lands. Granting of access remains the owner’s responsibility and trespass is handled by local law enforcement authorities. Federal river-administering agencies do, however, work closely with landowners to minimize problems through brochures and maps, signs, etc., and many landowners feel they are better off with the agency taking some responsibility.

Section 10(a) of the Wild and Scenic Rivers Wild & Scenic Rivers Act directs that:

Each component of the national wild and scenic rivers system shall be administered in such manner as to protect and enhance the values which caused it to be included in said system without, insofar as is consistent therewith, limiting other uses that do not substantially interfere with public use and enjoyment of these values.

In its technical report on managing wild and scenic rivers (Wild and Scenic River Management Responsibilities (2002)) the...

Landowners can charge a fee for crossing private lands to fish, except where a public access easement exists. The designation of a wild and scenic river does not change landowner rights unless all, or a portion of those use rights, are acquired from the landowner.

Corridors may not exceed an average of 320 acres per river mile over the designated portion of the river (except on certain other rivers as specified by Congress and in Alaska, which is 640 acres for rivers located outside national parks). Agencies delineate boundaries based on natural or manmade features (canyon rims, roads and ridge tops, etc.) and legally identifiable property lines.

Yes, a CRMP is developed in compliance with the NEPA. The purpose and need for the proposed action is to protect and enhance the values for which the river was designated (free-flowing condition, water quality, and outstandingly remarkable values), within its classification(s). The proposed action establishes appropriate goals, objectives, and/or desired conditions to meet those purposes. Alternative courses of actions are developed and analyzed relative to achieving overall goals and desired conditions within the wild and scenic river corridor. A “no action” alternative, representing the...

No, there is no statutory requirement that a CRMP be revisited in a specified timeframe. However, the federal wild and scenic river-administrator should periodically review monitoring information to determine if there is a need for change in existing direction to ensure values are protected and enhanced. Agency unit-wide plans that are revised following a CRMP-specific plan amendment will follow individual agency practices for plan revision. In some cases, this may include updating the CRMP during the agency unit-plan revision cycle.

For state-designated rivers, a governor may submit an application to the Secretary of the Interior under Section 2(a)(ii) of the Act.  If found eligible, and if sufficient protection is afforded by the state, the Secretary may make the designation.  Rivers designated in this manner continue to be administered by the state (sometimes with assistance from local governments), except for any federal lands along the river.  If there are federal lands located along the river, the state and federal river-administering agencies may enter into an agreement to outline federal/state...

Once such a river segment has been found to be ineligible, the agency will manage the river and its corridor based on the underlying management direction in its programmatic plan and need no longer protect it as a potential wild and scenic river.

The requirements specified for a CRMP in Section 3(d)(1) are most often developed through a separate-in-time planning process. This can result in either an amendment to the direction in the agency’s unit-wide plan o a stand-alone plan, depending on agency practices. For designated rivers that are separate NPS units, the CRMP is the General Management Plan (e.g., St. Croix National Scenic Riverway).

Rivers in Alaska outside of national parks and Elkhorn Creek in Oregon (640 acres per river mile) exceed the 320 acre average.

There are three instances when federal agencies assess eligibility: 1) at the request of Congress through specific authorized studies; 2) through their respective agency inventory and planning processes; or 3) during National Park Service evaluation of a Section 2(a)(ii) application by a state. River areas identified through the inventory phase are evaluated for their free-flowing condition and must possess at least one outstandingly remarkable value.

No. Navigability determinations are based on factors other than wild and scenic river designation. Because of this, designation does not affect ownership of the submerged lands [or minerals lying] under the river.

It is important to develop and apply standardized criteria through a documented evaluation process that may include a screening for potential wild and scenic rivers. If there doubt, evaluate the river according to the criteria in the Wild & Scenic Rivers Act, i.e., free-flowing condition and outstandingly remarkable values.

Section 13(c) of the Wild & Scenic Rivers Act expressly reserves the quantity of water necessary to protect river values, including water quality and flow-dependent outstandingly remarkable values. This reservation of water is called a federal reserved water right and is generally adjudicated in a state court (e.g., basin-wide adjudication). River designation does not supersede existing, valid water rights.

Refer also to CRS Report for Congress, The Wild and Scenic Rivers Act and Federal Water Rights, by Cynthia Brougher (January 9, 2009).

 

...

Yes. The “equal footing” principle of the Constitution and the Submerged Lands Act of 1953 afford each state the ownership of lands and natural resources under navigable rivers. These submerged lands generally extend from bank-to-bank or to the mean or ordinary high water mark.

Yes. There are four other principal agencies with authority on rivers, including wild and scenic rivers, in the United States. The EPA has authority to protect water quality; the Army Corps of Engineers (ACOE) has jurisdiction for water resources projects; the U.S. Coast Guard (USCG) has jurisdiction on inland navigable waters, vessel inspecting and licensing, safety and boating enforcement, aids to navigation, and permitting of bridges; and the Federal Energy Regulatory Commission (FERC) has authority to license the construction of hydroelectric projects.

Boundaries are measured from the ordinary high water mark of the outermost stream channel. That is, boundaries will be measured from the outermost braid unless otherwise specified by Congress. This is typically considered during the suitability determination and in the development of the final river corridor boundary.

The CRMP for rivers designated on or after January 1, 1986, is to be completed within three full-fiscal years after the date of designation or as otherwise specified, with a notice of completion and availability published in the Federal Register. For rivers designated before this date, Section 3(d)(2) requires review of the CRMP to determine if it conforms to Section 3(d)(1). This provision allowed ten years to update pre-1986 plans through the planning processes of river-administering agencies. Note: This 10-year period expired January 1, 1996.

Corridor boundaries are established to protect the free-flowing condition, water quality, and outstandingly remarkable values for which the river was designated. Generally, the corridor width for designated rivers cannot exceed an average of 320 acres per mile which, if applied uniformly along the entire designated segment, is one-quarter of a mile (1,320 feet) on each side of the river. Boundaries may be wider or narrower, but are not to exceed the 320 acre average per mile per Section 3(b) of the Wild & Scenic Rivers Act without approval by Congress. The acreage of any islands...

Yes, a federal reserved water right is generally adjudicated in state court (e.g., basin-wide adjudication) in the western United States. It is less clear how federal reserved water rights are adjudicated in the eastern United States. Contact a staff expert and/or legal counsel when trying to protect water quantity.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager should consult with staff with water rights expertise and, as necessary, seek legal counsel....

Local government entities are encouraged by federal wild and scenic river-administering agencies to provide for the protection of wild and scenic river values in their land use plans, including the use of zoning and other land use measures. Their participation in development of the comprehensive river management plan (CRMP) in areas of mixed ownership is essential to ensure an enduring planning strategy that protects river values and respects the rights of landowners. In some cases, local governments have chosen to strengthen land-use requirements during a wild and scenic river study, in...

Yes.  For purposes of eligibility evaluation, the volume of flow is sufficient if it is enough to sustain or complement the outstandingly remarkable values identified within the segment.  Rivers with intermittent or non-perennial flows exist within the National Wild & Scenic Rivers System and may be representative of rivers within particular physiographic regions.

The federal government has rarely exercised its eminent domain powers with respect to wild and scenic rivers. Of the 226 rivers in the National Wild & Scenic Rivers System as of June 2022, condemnation for fee title has been used on only four rivers. Nearly all of the federal government’s use of condemnation occurred in the early years of the Wild & Scenic Rivers Act’s implementation when the attitudinal climate was one of federal acquisition. Similarly, the use of scenic easement condemnation has also been used very rarely, and then only on seven rivers, all designated prior to...

Congress may classify the river upon the date of designation or authorize classification by the managing agency.  In the latter case, managing agencies have one year to finalize the boundary, identify the appropriate classification, and publish a notice in the Federal Register.  The agency has three years to complete a management plan.  For Section 2(a)(ii) rivers, classification would be established when the Secretary of the Interior designates the river.

The need to amend a segment division should be identified as a management concern/public issue during the planning process and considered in establishment of the initial boundary. The proposed amendment associated with establishment of initial boundaries must be undertaken with full public input and disclosure and is often completed during development of the comprehensive river management plan (CRMP) as a basis to make a recommendation to Congress to amend the Wild & Scenic Rivers Act.

The river-administering agency can only recommend such a change to Congress. A subsequent...

The Wild & Scenic Rivers Act does not specifically mention aquatic or upland non-indigenous species. While non-indigenous species may be introduced—provided that doing so is not contrary to another law or the policy of the managing agency, and would not result in the degradation to the river’s values—the use of native species is generally preferred. Indirect impacts of introducing non-indigenous species, e.g., increasing recreational fishing, should also be considered. Additional guidance for a specific river is usually included in its management plan.

When Congress proposes a bill to designate an eligible river for which a suitability study has not been completed, the potential river-administering agency should endeavor to:

  1. Describe the resource and social factors typically evaluated in a study;
  2. Identify potential issues; and
  3. Assess its ability to manage the recommended component as a wild and scenic river.

This information provides the basis for the Administration’s decision to support or oppose the proposed designation.

The river-administering agency must take the actions necessary to remedy adverse impacts and/or show measurable progress in addressing identified adverse effects. The Wild & Scenic Rivers Act gives river-administering agencies authority to adjust or eliminate livestock grazing, or any other commercial use, if doing so is necessary to meet the protection and enhancement standard.

No. The river study, enabling legislation, and subsequent management planning process will consider how best to protect river values while recognizing private property rights.

The government typically provides technical assistance to find ways to alleviate or mitigate the actual or potential threat(s). Purchasing a partial right (easement) or the property in fee title is usually the last resort. If an easement is purchased, the owner would sell certain development rights and receive a payment, yet retain title to the land.

No.  The Interagency Wild & Scenic River Guidelines state, “There are no specific requirements concerning the length or the flow of an eligible river segment.  A river segment is of sufficient length if, when managed as a wild, scenic or recreational river area, the outstandingly remarkable values are protected.  Flows are sufficient if they sustain or complement the outstandingly remarkable values for which the river was designated.

Some examples of other similar outstandingly remarkable values include botanical, hydrological, paleontological, scientific, or heritage values.

Prior to completion of the CRMP, proposed projects and new decisions (e.g., issuance of a special-use permit) on federal lands are evaluated by the wild and scenic river-administering agency to ensure they protect and, to the extent possible, enhance river values (free-flowing condition, water quality and outstandingly remarkable values). The necessary evaluation framework is a detailed description of the existing conditions of these values at the time of designation. Absent this information it may not be possible to evaluate the effects of an activity relative to the non-degradation and...

Wild and scenic river study reports are prepared in three instances:

  1. When Congress authorizes a study pursuant to Section 5(a) of the Wild & Scenic Rivers Act.

  2. For eligible rivers that have also been determined suitable by a federal land management agency pursuant to Section 5(d)(1) of the Wild & Scenic Rivers Act, when the agency deems it appropriate to forward the recommendation.

  3. For state-nominated Section 2(a)(ii) rivers, the National Park Service prepares a report determining whether the candidate river meets the requirements of...

Wild and scenic river designations generally cause property values to remain stable or increase. For example, see Economic Benefits of Conserved Rivers: An Annotated Bibliography (Porter, B., Collier, S., Becerra, N., and Schultz, J. 2001. National Park Service – Rivers and Trails Conservation and Assistance Program, Washington, DC. 27pp.).

No. The designation does not supersede existing, valid water rights.

 

Water law is a complex legal area, and water rights are a highly contentious issue. Whenever a water allocation issue arises, a river manager should consult with staff with water rights expertise and, as necessary, seek legal counsel.

River access is evaluated in the land use planning process.  Specific access needs for public enjoyment, as well as any limitations, are determined in the river management plan.  In keeping with the requirements of the Wild & Scenic Rivers Act, “wild” rivers are generally inaccessible, except by trail (no roads); “scenic” rivers are accessible by road, which generally don’t parallel the river; and “recreational” rivers may have parallel or crossing road and railroad access.

Benefits may include, but are not limited to, providing managers tools or mechanisms to protect free-flowing condition, i.e., protection of river values through the assessment of hydroelectric facilities or water resource development projects within the designated reach; protection and enhancement of water quality and outstandingly remarkable values; and, if a river’s management plan objective, promotion of economic development, tourism, or recreational use. Based on current limited studies, indications are that property values remain stable or increase on designated rivers. This is often...